20230329_145502.jpg

A residential building in Mevaseret Zion

Second opinion and an economic solution for establishing 2 buildings with 9 upper floors above 2 underground floors on the site where an old lime pit was discovered.

The challenge:

A residential lot that is located over a pit that was used to produce lime and filled in an uncontrolled manner with local fill. The solution given by the previous consultant made the project very expensive.

The solution:

First building: reclamation of the land with a network of concrete columns and the foundation of the buildings on a barge (raft).

Second building: will be built on micro file stilts.

The execution will start from the first building and after the completion of the foundation, the need for changes in the second building will be examined.