top of page
P80724-130419.jpg

Sha'are Zedek Hospital underground parking lot, Jerusalem

A foundation solution for the parking lot that includes monitoring the implementation and providing local solutions that resulted in savings of millions of shekels in the project's finishing costs.

The challenge:

Quarrying to a depth of about 30 m adjacent to an active hospital and urban streets.

The solution:

Close geological and engineering monitoring and accompaniment at the beginning of the deposition and during the entire quarrying allowed significant adjustment and lowering of the support elements, according to the findings.